Our approach to risk management within asset creation in the
water and wastewater industry employs a stage gate approach as
shown here:
Risk management within asset creation (Zoom)
The approach to maximising efficiency is to seek the least whole
life cost solution with the optimum risk and value balance. The
approach may be streamlined for smaller projects as appropriate –
the one presented above is for larger complex projects.
Our risk management methodology is closely linked to the management
of scope, cost and schedule. We believe that effective management
of these 4 areas –
"The 4 Pillars"
– delivers.
The key principles of The 4 Pillars (Zoom)
The ability to deliver projects with ever increasing efficiency
demands tight management of risk. The key principles underlining
our approach are:
- Collaboration between parties so that all risks are laid
bare
- Clear assignment of risk between parties
- Active management of risk to mitigate effectively at least
cost
We use statistical tools to understand the distribution of cost and
schedule risk and other tools to map change in risk through time
such as illustrated
here:
Understanding the distribution of costs (Zoom)
Integral with each stage are facilitated workshops.
RVM1 Initial risk assessment
The purpose of this stage gate is to agree a statement of the
business problem and an initial risk log including a view of the
risk impact on cost and schedule. In addition an outline solution
is agreed including its outline scope, cost, schedule and risk.
This stage gate is required in the preparation of the business
plan.
RVM2 Programme and sub-programme agreement
The purpose of this stage gate is to agree project bundling into
efficient programmes of work and thence allow release of an
instruction to procure services.
RVM3 Options freeze
The purpose of this stage-gate is to agree the options that will be
taken forward for design and costing. This stage-gate is intended
to avoid the situation where additional options are identified at
an inappropriate late stage causing delay due to re-working of
designs and cost estimates.
RVM4 Solution freeze
The purpose of this stage-gate is to select the single option that
will be taken forward for development and detailed design. This is
a key stage-gate and, to avoid delay, effort should be made to
ensure that this meeting only has to be called once for each
project. For this meeting to be effective, it is essential that
sufficient data be provided to make a risk and value judgement
between the options. The input data for the meeting should be
clearly defined and should include for each option: a description,
a list of advantages and disadvantages, a cost and risk. In
outline, the output of this meeting should be an agreed complete
scope of work for the project with justification for its
selection.
RVM5a Design review 1
RVM5a is a key stage-gate and is carried out at layout level to
agree the overall concepts of the solution before more detailed
design is commenced.
RVM5b Design review 2
RVM5b is carried out at general arrangement level detail for
sections of the works that have been identified as being
appropriate to review separately. Close attention must be paid to
the interfaces between the sections. A checklist approach for
design review will be developed and adopted where appropriate.
After this review, drawings, modified as necessary, should be able
to be issued ‘for construction’.
RVM6 Post project delivery review
The purpose of this stage gate is to review the effectiveness of
the delivered project and permit feedback.
RVM7 Operational review
The purpose of this stage gate is to agree the actual operational
performance of the asset against criteria agreed at RVM5 and permit
further feedback.